One of the most popular methods to understand if a team is doing SCRUM or not is through the use of what is called “Nokia Test”. It is a very simple yet very strict test and almost 80% of teams who claim to be doing SCRUM do not pass even Level 1. Here is an overview of the test:
LEVEL 1
- Iterations must be time-boxed to less than six weeks / Do your sprints start and end on planned dates
- Is the software completely tested and working at the end of an iteration
- Can the iteration start before specification is complete
LEVEL 2
- Does the team know who the product owner is
- Is there a product backlog prioritized by business value
- Does the product backlog have estimates created by the team
- Does the team generate its burndown charts and knows its velocity
- Does the team have outside people disrupting the work of the team during the sprint